careers@hallconstructors.com

Projects | Commercial / Institutional | Hall Constructors

showing 1 to 10 of 17 on page 1 | 1  2  
Contract Value

$2,750,000

Location

550 Carmi Ave, Penticton, BC V2A 3G6

Completion Date

November 30, 2017

Description

Project consists of select demolition of the Penticton Regional Hospital, bulk/detailed/mechanical excavation for the New Patient Care Tower and Parkade, lock block and secant pile retaining wall systems and site servicing (vital power duct bank, propane and oxygen feeds, water main, and drainage).

Contract Value

$1,706,000

Location

Orchards Commons, UBC Campus

Completion Date

March 31, 2016

Description

Offsite work includes installation of storm, sanitary, water, hydro/tel and gas mains on busy West Mall and Agronomy Road around the new Vantage College facilities. Trench excavation up to six meters deep, conflict avoidance with existing utilities, and traffic management present constant challenges for the crew. Onsite work includes installation of storm, sanitary mains as well a 175m3 sistern system consists of 2.4m x 2.4m segments of precast box culvert 5m deep, all done in extremely confined space.

Contract Value

$350,000

Location

KLO Road, Kelowna, BC

Completion Date

March 31, 2016

Description

Parking Facility - Earthworks, drainage, graveling and paving. Main challenge was working on Campus with a multitude of other Tradespeople. This required extra vigilance for operators to be aware of who is around them.

Contract Value

$680,000

Location

Anders Road, West Kelowna, BC

Completion Date

March 31, 2016

Description

Re-development of Shopping Centre site including offsite/onsite servicing, grading, curb & sidewalks, paving, Hydro-Tel and streetlighting.

Contract Value

$3,650,000

Location

3075 Takaya Drive, North Vancouver

Completion Date

November 30, 2015

Description

Excavated and hauled offsite 46,000 m3 of non-contaminated and 10,000 m3 of contaminated (CL+ & RL+) soil. Placed 11,000 m3 of imported fill. In addition, 3,700m2 of SedimentLok 200+ m2 of SierraScape retaining wall were built for erosion control and slope stablization. Job completed on budget and ahead of schedule.

Contract Value

$382,400

Location

19498 - 92 Avenue, Surrey, B.C.

Completion Date

October 15, 2015

Description

Clearing, excavation, granular fill, gravel installation, and asphalt paving. BD Hall proposed a modification of pavement structure which permitted installation of asphalt paving within three weeks of startup during busy paving season - this allowed Finning additional time to re-position equipment to other facilities prior to arrival of new equipment.

Contract Value

$2,030,000

Location

UBC Athletics Precinct - Wesbrook Mall & 16th Avenue, UBC

Completion Date

September 30, 2015

Description

Faced with the challenge of a very tight schedule and proximity to existing facilities, the crew installed storm, sanitary, water, hydro/tel, gas mains and a 250 m3 cast-in-place concrete detention tank. The project finished on time and on budget.

Contract Value

$1,840,000

Location

University Boulevard & East Mall, UBC Campus

Completion Date

September 30, 2015

Description

Scope of work includes ** Watermain upgrade, ** Demolition of existing sidewalk, road structure and concrete slab, replaced with new landscaping features and concrete pavers. ** Construction of a new 450m3 cast in place concrete detention tank.

Contract Value

$8,408,000

Location

Burnaby Campus of Simon Fraser University

Completion Date

September 30, 2015

Description

Project included 3.5km of road re-construction, 7,000m of curb & gutter, 700m of concrete sidewalk, a roundabout, 3km of multi-use path, intersection improvements, street lighting, sewer and watermain construction, detention pond and landscape works. Scope: - Remove existing concrete and asphalt road - Reuse road concrete as base of multi-use pathway - Reconstruct road, curbs and gutters - Construct new detention pond - Lighting and signalized intersection - Landscaping

Contract Value

$339,000

Location

Sustainability Street, UBC Campus

Completion Date

December 31, 2014

Description

Scope of work including replacing existing 200mm watermain with 250mm, site demolition, grading, underground utilities.

showing 1 to 10 of 17 on page 1 | 1  2