careers@hallconstructors.com

Projects | Commercial / Institutional | Hall Constructors

showing 1 to 10 of 17 on page 1 | 1  2  
Contract Value

$8,408,000

Location

Burnaby Campus of Simon Fraser University

Completion Date

September 30, 2015

Description

Project included 3.5km of road re-construction, 7,000m of curb & gutter, 700m of concrete sidewalk, a roundabout, 3km of multi-use path, intersection improvements, street lighting, sewer and watermain construction, detention pond and landscape works. Scope: - Remove existing concrete and asphalt road - Reuse road concrete as base of multi-use pathway - Reconstruct road, curbs and gutters - Construct new detention pond - Lighting and signalized intersection - Landscaping

Contract Value

$5,000,000

Location

Willingdon Ave & Lougheed Highway, Burnaby

Completion Date

December 20, 2014

Description

Hall Constructors was contracted by EllisDon to complete the offsite civil work at Brentwood Mall for Shape Properties. This extensive project included utility relocation and roadwork upgrades which needed to be completed before redevelopment of the existing mall could begin. While this work was on two very busy roadways, Hall worked closely with the City, Owner and Consultants to execute the work with minimal impacts to the public.

Contract Value

$4,375,000

Location

Marine Drive and Taylor Way, District of West Vancouver, BC

Completion Date

May 15, 2013

Description

Scope includes removal of two overpass structures on Marine Drive, installation of underground utilities, construction of signalized intersection at overpass location, signalization of another intersection, re-alignment of Parking Lots and Landscaping.

Contract Value

$3,650,000

Location

3075 Takaya Drive, North Vancouver

Completion Date

November 30, 2015

Description

Excavated and hauled offsite 46,000 m3 of non-contaminated and 10,000 m3 of contaminated (CL+ & RL+) soil. Placed 11,000 m3 of imported fill. In addition, 3,700m2 of SedimentLok 200+ m2 of SierraScape retaining wall were built for erosion control and slope stablization. Job completed on budget and ahead of schedule.

Contract Value

$2,750,000

Location

550 Carmi Ave, Penticton, BC V2A 3G6

Completion Date

November 30, 2017

Description

Project consists of select demolition of the Penticton Regional Hospital, bulk/detailed/mechanical excavation for the New Patient Care Tower and Parkade, lock block and secant pile retaining wall systems and site servicing (vital power duct bank, propane and oxygen feeds, water main, and drainage).

Contract Value

$2,500,000

Completion Date

November 30, 2014

Description

Storm and Sanitary upgrades, road re-construction and improvements to Knight Street, Jacombs Road and Sweden Way, BC Hydro and Telus civil installation.

Contract Value

$2,030,000

Location

UBC Athletics Precinct - Wesbrook Mall & 16th Avenue, UBC

Completion Date

September 30, 2015

Description

Faced with the challenge of a very tight schedule and proximity to existing facilities, the crew installed storm, sanitary, water, hydro/tel, gas mains and a 250 m3 cast-in-place concrete detention tank. The project finished on time and on budget.

Contract Value

$2,024,000

Location

Downtown, Vancouver, BC

Completion Date

May 15, 2014

Description

Scope includes removal of existing pumps and electrical works, installation of temporary lighting and ventilation system and filling this 800m long tunnel with cellular concrete.

Contract Value

$1,840,000

Location

University Boulevard & East Mall, UBC Campus

Completion Date

September 30, 2015

Description

Scope of work includes ** Watermain upgrade, ** Demolition of existing sidewalk, road structure and concrete slab, replaced with new landscaping features and concrete pavers. ** Construction of a new 450m3 cast in place concrete detention tank.

Contract Value

$1,706,000

Location

Orchards Commons, UBC Campus

Completion Date

March 31, 2016

Description

Offsite work includes installation of storm, sanitary, water, hydro/tel and gas mains on busy West Mall and Agronomy Road around the new Vantage College facilities. Trench excavation up to six meters deep, conflict avoidance with existing utilities, and traffic management present constant challenges for the crew. Onsite work includes installation of storm, sanitary mains as well a 175m3 sistern system consists of 2.4m x 2.4m segments of precast box culvert 5m deep, all done in extremely confined space.

showing 1 to 10 of 17 on page 1 | 1  2