careers@hallconstructors.com

Projects | Excavation and Shoring | Hall Constructors

showing 1 to 10 of 37 on page 1 | 1  2  3  4    
Contract Value

$14,500,000

Location

39 Smithe Street, Vancouver, BC

Completion Date

January 15, 2016

Description

Project consisted of select demolition of BC Place, Jet Grout Piles, Driven Pile Piles, Bulk / Detailed / Mechanical Excavation complete with Shotcrete and Anchor Shoring system. Total volume of material removed was 160,000 m3 of which approximately 45,000 m3 was contaminated. Schedule was a major factor on this project and Hall Constructors was able to deliver the excavation 2 months ahead of schedule.

Contract Value

$5,002,000

Location

McKinley Beach Drive, Kelowna, BC

Completion Date

October 31, 2017

Contract Value

$4,000,000

Location

5501 Boundary Rd, Vancouver

Completion Date

March 18, 2016

Description

The contract for this project involved utility relocation, as well as excavation and shoring for Phase 2 of Wall Financial's Central Park project. First, Hall Constructors relocated 110 meters of 1350 diameter storm pipe and 110 meters of 750 diameter sanitary pipe which are both owned by Metro Vancouver. Once those utilities were moved off of the property, Hall completed the 43,000 m3 excavation by using a combination of secant piles and conventional shotcrete to shore the dig. This project also included installation of BC Hydro, Telus and storm/sanitary services for both phases of the development.

Contract Value

$3,780,000

Location

1300 Block of Marine Drive, West Vancouver, BC

Completion Date

December 21, 2015

Description

Project consisted of site preparation works to allow for the installation of 354 - 1 metre diameter Secant Piles to an average depth of 17 metres below existing grade.

Contract Value

$3,325,000

Location

Ioco Road & Barnet Highway, Port Moody, BC

Completion Date

March 31, 2014

Description

Project consisted of the Bulk/Detailed Excavation of approximately 17,000 m3 for the East and West Head House structures. The excavation was supported by a shoring design consisting of pipe piles, fiberglass anchors, IBO Anchors and Secant Piles. Once these excavations were completed, we completed a 8,000 m3 excavation in 48 hours to facilitate the pushing of the Box Tunnel followed by the rebuilding of the roadway in 24 hours.

Contract Value

$2,830,000

Location

Coquitlam, BC

Completion Date

February 29, 2012

Description

Construction started in July 2011 with the aim being to prepare a proposed site at Pipeline Road and David Avenue in Port Coquitlam for construction of a multi-story apartment complex complete with 3 levels of parkade. Preparation of the site involved pile driving, shotcrete and anchoring, bulk excavation, detail excavation and rock removal. A large portion of the work was bulk excavation with 60,000 cubic metres removed from site. Project completion was February 2012.

Contract Value

$2,400,000

Location

2513 Clarke St, Port Moody

Completion Date

December 31, 2016

Description

This project includes secant pile drilling and bulk excavation of 24,000 m3 of material for Townline Construction. The poor soil conditions at the footing level require a raft slab foundation.

Contract Value

$2,330,000

Location

1779 Douglas Rd, Burnaby

Completion Date

July 31, 2013

Description

This 40,000 m3 excavation and shoring project made wade way for a high-rise residential tower in Burnaby’s Brentwood neighborhood, which was managed by Marcon Construction. Under approval from Environment Canada, Hall Constructors implemented ocean disposal of the clean, excavated material, as this is the most effective and economical option for the Owner.

Contract Value

$2,320,000

Location

88 West 1st Ave, Vancouver

Completion Date

July 31, 2013

Description

Hall Constructors completed this 43,000 m3 excavation and shoring project for Mondiale Development in 2013. The site was located on the historical ocean shoreline and had previously been infilled with contaminated material. Hall worked with the Owner and Environmental Consultant to send all contaminants to appropriate remediation facilities, then obtained approval from Environment Canada to dispose of the clean, native material via ocean dumping.

Contract Value

$2,237,000

Location

West Mall & Agronomy Road, UBC

Completion Date

March 31, 2016

Description

Haul & dispose off site 25,000m3 of bulk & detailed excavation, backfill behind external perimeter walls and installation of 1,800 lm of IBO anchors and 1,000 m2 of shotcrete shoring.

showing 1 to 10 of 37 on page 1 | 1  2  3  4