careers@hallconstructors.com

Projects | Excavation and Shoring | Hall Constructors

showing 1 to 10 of 36 on page 1 | 1  2  3  4    
Contract Value

$14,500,000

Location

39 Smithe Street, Vancouver, BC

Completion Date

January 15, 2016

Description

Project consisted of select demolition of BC Place, Jet Grout Piles, Driven Pile Piles, Bulk / Detailed / Mechanical Excavation complete with Shotcrete and Anchor Shoring system. Total volume of material removed was 160,000 m3 of which approximately 45,000 m3 was contaminated. Schedule was a major factor on this project and Hall Constructors was able to deliver the excavation 2 months ahead of schedule.

Contract Value

$610,000

Location

179 Main Street, Vancouver

Completion Date

December 31, 2016

Description

Hall will be completing this bulk excavation project for Marcon Construction. One portion of the excavation will be shored without the use of soil anchors, and will utilize steel beams and vertical piles to support the excavation from within the site. Hall Constructors will also be working with the adjacent fire hall to maintain their emergency service access throughout the project.

Contract Value

$2,400,000

Location

2513 Clarke St, Port Moody

Completion Date

December 31, 2016

Description

This project includes secant pile drilling and bulk excavation of 24,000 m3 of material for Townline Construction. The poor soil conditions at the footing level require a raft slab foundation.

Contract Value

$850,000

Location

2358 153 St, Surrey

Completion Date

October 30, 2016

Description

Hall Constructors completed both the excavation and civil work for Marcon Construction on this project. Though the excavation was only 10,000 m3, it was completed on schedule and on budget. The civil work will be completed later in the year, once the building has been finished. The completion of this project is meaningful, as it will provide independent, affordable living for members of the Semiahmoo House Society and the local community.

Contract Value

$800,000

Location

1785 West 4th Avenue, Vancouver

Completion Date

August 11, 2016

Description

Hall Constructors was contracted by Darwin Construction to complete this 8,000 m3 excavation and shoring project associated with a new commercial development at the northeast corner of the intersection between Burrard Street and West 4th Avenue. The bottom portion of the excavation proved difficult due to very dense sandstone and siltstone which required extensive hydraulic splitting in order to break up and remove soil from site. In addition, special care was taken to ensure protection of the neighbouring surf and snowboard shop to the east.

Contract Value

$2,237,000

Location

West Mall & Agronomy Road, UBC

Completion Date

March 31, 2016

Description

Haul & dispose off site 25,000m3 of bulk & detailed excavation, backfill behind external perimeter walls and installation of 1,800 lm of IBO anchors and 1,000 m2 of shotcrete shoring.

Contract Value

$4,000,000

Location

5501 Boundary Rd, Vancouver

Completion Date

March 18, 2016

Description

The contract for this project involved utility relocation, as well as excavation and shoring for Phase 2 of Wall Financial's Central Park project. First, Hall Constructors relocated 110 meters of 1350 diameter storm pipe and 110 meters of 750 diameter sanitary pipe which are both owned by Metro Vancouver. Once those utilities were moved off of the property, Hall completed the 43,000 m3 excavation by using a combination of secant piles and conventional shotcrete to shore the dig. This project also included installation of BC Hydro, Telus and storm/sanitary services for both phases of the development.

Contract Value

$3,780,000

Location

1300 Block of Marine Drive, West Vancouver, BC

Completion Date

December 21, 2015

Description

Project consisted of site preparation works to allow for the installation of 354 - 1 metre diameter Secant Piles to an average depth of 17 metres below existing grade.

Contract Value

$603,000

Location

7928 & 7988 Yukon Street, Vancouver, BC

Completion Date

December 15, 2015

Description

The project consisted of an approximate 13,100 m3 Bulk & Detail excavation including shotcrete & Anchor shoring. Limited access and a long and narrow site made this project a challenge to complete on schedule.

Contract Value

$1,115,000

Location

3205 Mountain Highway

Completion Date

December 15, 2015

Description

This 15,000 m3 excavation and shoring project was completed for Marcon Construction in 2015. Though the site proved difficult, Hall was able to work with the Owner to deliver the excavation on time. Extra measures were taken to ensure that the neighboring creek was protected and that silt from the excavation was diverted away from the waterway. Hall also used it's ocean dumping facility to provide the most economic soil disposal option on this project.

showing 1 to 10 of 36 on page 1 | 1  2  3  4