Inlet Centre Station - Evergreen Line

Contract Value

$3,325,000

Location

Ioco Road & Barnet Highway, Port Moody, BC

Completion Date

March 31, 2014

Description

Project consisted of the Bulk/Detailed Excavation of approximately 17,000 m3 for the East and West Head House structures. The excavation was supported by a shoring design consisting of pipe piles, fiberglass anchors, IBO Anchors and Secant Piles. Once these excavations were completed, we completed a 8,000 m3 excavation in 48 hours to facilitate the pushing of the Box Tunnel followed by the rebuilding of the roadway in 24 hours.