Wall Centre Central Park - Phase 2

Contract Value

$4,000,000

Location

5501 Boundary Rd, Vancouver

Completion Date

March 18, 2016

Description

The contract for this project involved utility relocation, as well as excavation and shoring for Phase 2 of Wall Financial's Central Park project. First, Hall Constructors relocated 110 meters of 1350 diameter storm pipe and 110 meters of 750 diameter sanitary pipe which are both owned by Metro Vancouver. Once those utilities were moved off of the property, Hall completed the 43,000 m3 excavation by using a combination of secant piles and conventional shotcrete to shore the dig. This project also included installation of BC Hydro, Telus and storm/sanitary services for both phases of the development.