careers@hallconstructors.com

Projects | Hall Constructors

showing 1 to 10 of 73 on page 1 | 1  2  3  4  5  6  7  8    
Contract Value

$14,500,000

Location

39 Smithe Street, Vancouver, BC

Completion Date

January 15, 2016

Description

Project consisted of select demolition of BC Place, Jet Grout Piles, Driven Pile Piles, Bulk / Detailed / Mechanical Excavation complete with Shotcrete and Anchor Shoring system. Total volume of material removed was 160,000 m3 of which approximately 45,000 m3 was contaminated. Schedule was a major factor on this project and Hall Constructors was able to deliver the excavation 2 months ahead of schedule.

Contract Value

$7,705,577.25

Location

Vancouver Landfill

Completion Date

November 1, 2017

Description

Work involves the installation of a layered cap onto a prepared, filled landfill or landfill area. The layers which make up the layered cap consist respectively of gravel, sand, geomembrane, geotextile and topsoil, with vegetation planted in the topsoil layer. In addition, gas works, including vertical extraction wells, piping/connections and appurtenances integrated with the layered closure system, are also installed.

The construction/installation of gas works within the Phase 3 SE and Phase 3NE areas are included in the Work. The City’s Consultant has prepared the Specifications and Drawings for the Work which includes, but is not limited to, the following work outlined further within Schedule 2 – Specifications and Drawings:

  • Earthworks
  • Landfill Closure
  • Leachate Management Upgrades
  • Surface Water Management Upgrades
  • Landfill Gas Management Upgrades
  • Infrastructure Upgrades and Miscellaneous Works
Contract Value

$630,000

Location

2513 Clarke St, Port Moody

Completion Date

September 30, 2017

Description

Hall Constructors is completing the offsite civil work on this project for Townline Construction. The work includes new Hydro, Telus, Shaw, street lighting and municipal service connections for the building, as well as sidewalk and road upgrades for the surrounding streets.

Contract Value

$2,530,000

Location

1308 Lonsdale Ave, North Vancouver

Completion Date

April 30, 2017

Description

Hall Constructors is completing the offsite civil work on this project for Onni. The work includes new curb, sidewalk and asphalt for the road surrounding the site, as well as extensive BC Hydro, street light and intersection signal upgrades. Hall has worked extensively with the Owner, City and local businesses to ensure that construction is safe and that disruptions are kept to a minimum. This is especially important due to the close proximity of the Lions Gate Hospital, city hall, fire hall, RCMP detachment and surrounding residential buildings.

Contract Value

$1,375,000

Location

7711 18th Street, Burnaby

Completion Date

February 28, 2017

Description

Hall Constructors is completing this initial phase of offsite civil work for Marcon Construction, which will provide access to Ledingham McAllister's master planned Southgate City. The work will include a new access road, complete with storm, sanitary, water, BC Hydro and street light upgrades as well as a fully signalized intersection at Griffith's Drive.

Contract Value

$610,000

Location

179 Main Street, Vancouver

Completion Date

December 31, 2016

Description

Hall will be completing this bulk excavation project for Marcon Construction. One portion of the excavation will be shored without the use of soil anchors, and will utilize steel beams and vertical piles to support the excavation from within the site. Hall Constructors will also be working with the adjacent fire hall to maintain their emergency service access throughout the project.

Contract Value

$2,400,000

Location

2513 Clarke St, Port Moody

Completion Date

December 31, 2016

Description

This project includes secant pile drilling and bulk excavation of 24,000 m3 of material for Townline Construction. The poor soil conditions at the footing level require a raft slab foundation.

Contract Value

$1,868,000.00

Location

Delta, BC

Completion Date

November 10, 2016

Description

Commercial truckers travelling through the Lower Mainland now have a convenient place to stop and rest, as the $2.8-million Nordel Way truck parking facility was officially opened today by Delta North MLA Scott Hamilton, on behalf of Transportation and Infrastructure Minister Todd Stone. “With so much of our economy relying on the movement of goods via truck, this facility is an important addition to our transportation infrastructure,” said Stone. “This is a safe, convenient place where drivers can take a break or grab a rest, and provides a good option for those who would otherwise park on a local street.” The new truck-parking facility is located on Nordel Way at Highway 91 in Delta, across from the Nordel commercial vehicle inspection facility. The facility has room for up to 40 heavy trucks to park overnight and includes lighting, washrooms, garbage cans and a sani-dump. Construction began in August and was complete on Nov 10 2016

Contract Value

$850,000

Location

2358 153 St, Surrey

Completion Date

October 30, 2016

Description

Hall Constructors completed both the excavation and civil work for Marcon Construction on this project. Though the excavation was only 10,000 m3, it was completed on schedule and on budget. The civil work will be completed later in the year, once the building has been finished. The completion of this project is meaningful, as it will provide independent, affordable living for members of the Semiahmoo House Society and the local community.

Contract Value

$800,000

Location

1785 West 4th Avenue, Vancouver

Completion Date

August 11, 2016

Description

Hall Constructors was contracted by Darwin Construction to complete this 8,000 m3 excavation and shoring project associated with a new commercial development at the northeast corner of the intersection between Burrard Street and West 4th Avenue. The bottom portion of the excavation proved difficult due to very dense sandstone and siltstone which required extensive hydraulic splitting in order to break up and remove soil from site. In addition, special care was taken to ensure protection of the neighbouring surf and snowboard shop to the east.

showing 1 to 10 of 73 on page 1 | 1  2  3  4  5  6  7  8