Contract Value

$11,457,000

Location

Kelowna, BC

Completion Date

August 15, 2016

Description

Rocky Point 34 Lot Subdivision requiring 123,000 m3 of Earthworks, 1100 lm of Sanitary, Storm and Water works. Hydro, Telephone and Cable installation, curb & sidewalk plus 1300 m2 of Sierrascape retaining walls. Red Sky 33 Lot Subdivision requiring 1200 lm of Sanitary, Storm and Watermain. Hydro-Tel-Cable installation, curb & sidewalk paving and 2300 m2 Sierrascape retaining walls. Forest Edge Neighbourhood 63 Lot Subdivision requiring 55,000 m3 of Earthworks, 850 lm each Sanitary, Storm and Watermain. Hydro-Tel and Cable, curb, sidewalks, gravelling and paving.

Contract Value

$600,000

Location

W 12th Avenue & Cambie Street, Vancouver, B.C.

Completion Date

July 31, 2016

Description

Installation of storm & sanitary sewers from existing lane to W 12th Ave & Cambie St to facilitate closing of existing lane to create one residential complex out of two existing lots. Construction of 4m deep sewers on W 12th Ave. & Cambie St., major arterial roads, was only permitted on select weekends during the FIFA Women's World Cup Soccer Tournament; extensive traffic planning and control; all roadways required to be patched and fully operational prior to Monday morning rush hour. Extensive existing infrastructure, often unrecorded or not as shown, required significant on-the-fly modifications to maintain schedule.

Contract Value

$1,000,000

Location

Glenmore Landfill, Kelowna, BC

Completion Date

May 31, 2016

Description

McKinley Beach Lift Station #4 is scheduled to begin construction in mid-February 2016. The scope of work includes installation of a 12 ft diameter fibre-glass wet well, an electrical kiosk, a backup diesel generator and sanitary force-main that connects to the existing municipal infrastructure. The lift station will also contain a leachate treatment system that connects to the Glenmore Landfill's facility. The main challenges associated with this job will revolve around the high water table and de-watering works that will be required to maintain a safe excavation for the wet well. Also, onsite gas monitoring will occur throughout the project to ensure worker safety from any leeching contaminates within the excavation from the landfill. The lift station is financed by the City of Kelowna and the McKinley Hillside Limited Partnership and will serve McKinley's new lake-front subdivision development.

Contract Value

$5,100,000

Location

Glenmore Road & McKinley Road, Kelowna, BC

Completion Date

December 15, 2015

Description

Requiring 1800 lm of Water main, 8000 lm Sewer main and 6000 lm of Roadway restoration. Main challenge was the installation of 4-5m deep Sanitary main adjacent to busy roadways with 30% of the trenching in rock to be blasted or hammered.

Contract Value

$4,000,000

Location

206 St and 86th Ave, Langley

Completion Date

November 20, 2014

Description

108 lot site servicing including new roadworks and existing roadwork upgrades and utilities. Maintaining traffic during the road reconstruction and installation of utilities without interruptions were a challenge that Hall managed through good planning and timely work. Upon completion a quality product was delivered while improving access in and out of this community within the Township of Langley.

Contract Value

$1,387,000

Location

Coquitlam, BC

Completion Date

October 31, 2012

Description

Site servicing, utility installation and road works for a 34 lot residential subdivision located in Coquitlam.

Contract Value

$1,277,000

Location

148th Street and 61 Avenue, Surrey, BC.

Completion Date

September 30, 2012

Description

On & off-site servicing for a 91 unit townhouse site. The project consists of site servicing for a 91 unit townhouse site which includes 500m of new road construction, storm, sanitary and water services, electrical, hydro, Telus and cable connections. The project also consists of significant onsite earth works and approximately 100 lm of retaining construction.

Contract Value

$1,251,000

Location

76A Ave & 156 St, Surrey, BC.

Completion Date

August 31, 2012

Description

24 Lot Subdivision and Site Servicing. Scope of work consisting of tree clearing and lot preparation, utility install, roads and hard surface treatments.