careers@hallconstructors.com

Projects | Commercial / Institutional | Hall Constructors

showing 11 to 17 of 17 on page 2 |   1  2  
Contract Value

$1,528,000

Location

Langley, BC

Completion Date

June 30, 2011

Description

The Anthem Glover project involves the construction of an Automall Access road, including storm sewers, large underground detention system, water mains, curb & gutter, paving sidewalks, street lighting, traffic signals, and highway widening. The project is located at the busy intersection of Langley Bypass and Glover Road. After completion, the Automall will become one of City of Langley’s landmarks, selling high end luxury European make vehicles and is set to open in the summer of 2011. The large underground concrete storm water detention tank system, seventy meters in length and storing close to 4000m3 of storm water, is one of the most challenging and unique aspects of this large private development project.

Contract Value

$1,480,000

Location

Vancouver, BC

Completion Date

December 31, 2012

Description

The Great Northern Way Campus Lot “O” project involves clearing and grubbing and off-site disposal of vegetation and debris from the work area, installation and maintenance of erosion and sediment control facilities, stripping and earthworks for approximately 36,000 metric tonnes of road embankment construction, temporary lock-block retaining wall and retaining wall drainage.

Contract Value

$680,000

Location

Anders Road, West Kelowna, BC

Completion Date

March 31, 2016

Description

Re-development of Shopping Centre site including offsite/onsite servicing, grading, curb & sidewalks, paving, Hydro-Tel and streetlighting.

Contract Value

$603,700

Location

70th Ave & 194A Street, Surrey, BC

Completion Date

January 31, 2014

Description

This project consisted of a roadworks upgrade including utilities and streetlights.

Contract Value

$382,400

Location

19498 - 92 Avenue, Surrey, B.C.

Completion Date

October 15, 2015

Description

Clearing, excavation, granular fill, gravel installation, and asphalt paving. BD Hall proposed a modification of pavement structure which permitted installation of asphalt paving within three weeks of startup during busy paving season - this allowed Finning additional time to re-position equipment to other facilities prior to arrival of new equipment.

Contract Value

$350,000

Location

KLO Road, Kelowna, BC

Completion Date

March 31, 2016

Description

Parking Facility - Earthworks, drainage, graveling and paving. Main challenge was working on Campus with a multitude of other Tradespeople. This required extra vigilance for operators to be aware of who is around them.

Contract Value

$339,000

Location

Sustainability Street, UBC Campus

Completion Date

December 31, 2014

Description

Scope of work including replacing existing 200mm watermain with 250mm, site demolition, grading, underground utilities.

showing 11 to 17 of 17 on page 2 |   1  2