careers@hallconstructors.com

Projects | Excavation and Shoring | Hall Constructors

showing 1 to 10 of 42 on page 1 | 1  2  3  4  5    
Contract Value

$3,300,000

Location

1365 Davie Street, Vancouver, B.C.

Completion Date

March 31, 2019

Description

This 45,000 m3 excavation and shoring project was completed for Marcon Construction in late 2018 and early 2019 to assist in the construction of this modern twin tower development in Vancouver’s West End. The schedule was a major factor on this project and Hall Constructors was able to deliver the excavation on time and on budget.

Contract Value

$2,600,000

Location

401 SW Marine Drive, Vancouver

Completion Date

January 2, 2018

Description

This 65,000 m3 excavation and shoring project was completed for Centreville Construction in late 2016 and early 2017 to assist in the construction of 3 high rise apartments near the Canada Line. It consisted of 42 steel piles, 20,000 lineal feet of soil anchors, and 38,000 square feet of shotcrete shoring. The biggest challenge on this job was dealing with the large amount of rain and snow encountered throughout the fall and winter.

Contract Value

$1,690,000

Location

2289 Bellevue Avenue, West Vancouver

Completion Date

January 2, 2018

Description

Hall Constructors was contracted by Cressey Developments to complete this 31,000 m3 excavation and shoring project associated with a new residential development on the south side of Marine Drive in West Vancouver. The bottom portion of the excavation proved difficult due to very dense sandstone and siltstone which required extensive hoe-ramming in order to break up and remove the soils from site.

Contract Value

$1,200,000

Location

7864 208 Street, Langley

Completion Date

January 2, 2018

Description

This 65,000 m3 excavation and shoring project was completed for ENM Construction in late 2016 and early 2017 to assist in the construction of a midrise apartment in Northwest Langley. The site was large enough that no shotcrete shoring was required and all sides of the excavation were sloped. The biggest challenge on this job was dealing with the large amount of rain and snow encountered throughout the fall and winter.

Contract Value

$805,000

Location

5415 Lougheed Highway, Burnaby

Completion Date

January 2, 2018

Description

This 19,000 m3 excavation and shoring project was completed for Marcon Construction in late 2016 and early 2017 to assist in the construction of a townhouse development along Lougheed Highway. It consisted of 6,000 lineal feet of soil anchors, and 9,300 square feet of shotcrete shoring. The biggest challenge on this job was dealing with the large amount of groundwater which infiltrated the site from the north side.

Contract Value

$5,002,000

Location

McKinley Beach Drive, Kelowna, BC

Completion Date

October 31, 2017

Contract Value

$2,400,000

Location

2513 Clarke St, Port Moody

Completion Date

December 31, 2016

Description

This project includes secant pile drilling and bulk excavation of 24,000 m3 of material for Townline Construction. The poor soil conditions at the footing level require a raft slab foundation.

Contract Value

$610,000

Location

179 Main Street, Vancouver

Completion Date

December 31, 2016

Description

Hall will be completing this bulk excavation project for Marcon Construction. One portion of the excavation will be shored without the use of soil anchors, and will utilize steel beams and vertical piles to support the excavation from within the site. Hall Constructors will also be working with the adjacent fire hall to maintain their emergency service access throughout the project.

Contract Value

$850,000

Location

2358 153 St, Surrey

Completion Date

October 30, 2016

Description

Hall Constructors completed both the excavation and civil work for Marcon Construction on this project. Though the excavation was only 10,000 m3, it was completed on schedule and on budget. The civil work will be completed later in the year, once the building has been finished. The completion of this project is meaningful, as it will provide independent, affordable living for members of the Semiahmoo House Society and the local community.

Contract Value

$800,000

Location

1785 West 4th Avenue, Vancouver

Completion Date

August 11, 2016

Description

Hall Constructors was contracted by Darwin Construction to complete this 8,000 m3 excavation and shoring project associated with a new commercial development at the northeast corner of the intersection between Burrard Street and West 4th Avenue. The bottom portion of the excavation proved difficult due to very dense sandstone and siltstone which required extensive hydraulic splitting in order to break up and remove soil from site. In addition, special care was taken to ensure protection of the neighbouring surf and snowboard shop to the east.

showing 1 to 10 of 42 on page 1 | 1  2  3  4  5