careers@hallconstructors.com

Forensic Psychiatric Hospital - Flood Mitigation Project

Contract Value

$4,668,000

Location

Coquitlam, BC

Completion Date

June 15, 2015

Description

Construction of 40,000 m3 Earthen Flood Dyke, installation of sheetpile flood wall, relocation of existing utilities. Emergency access from Mary Hill Bypass including 12,000 m3 of Granular fill, an open bottom Arch culvert with Retaining Wall. Many difficulties presented themselves on this project, the most prevalent were sourcing and placing specified dyke fill material, driving plastic sheet piles into heavily consolidated ground plus working in and around a heavily secured facility.

| showing 1 to 1 of 1