Marine Gardens

Contract Value

$2,600,000

Location

401 SW Marine Drive, Vancouver

Completion Date

January 2, 2018

Description

This 65,000 m3 excavation and shoring project was completed for Centreville Construction in late 2016 and early 2017 to assist in the construction of 3 high rise apartments near the Canada Line. It consisted of 42 steel piles, 20,000 lineal feet of soil anchors, and 38,000 square feet of shotcrete shoring. The biggest challenge on this job was dealing with the large amount of rain and snow encountered throughout the fall and winter.