careers@hallconstructors.com

The Spot - Storm, Sanitary & Electrical Re-Routing

Contract Value

$600,000

Location

W 12th Avenue & Cambie Street, Vancouver, B.C.

Completion Date

July 31, 2016

Description

Installation of storm & sanitary sewers from existing lane to W 12th Ave & Cambie St to facilitate closing of existing lane to create one residential complex out of two existing lots. Construction of 4m deep sewers on W 12th Ave. & Cambie St., major arterial roads, was only permitted on select weekends during the FIFA Women's World Cup Soccer Tournament; extensive traffic planning and control; all roadways required to be patched and fully operational prior to Monday morning rush hour. Extensive existing infrastructure, often unrecorded or not as shown, required significant on-the-fly modifications to maintain schedule.