careers@hallconstructors.com

UBC Orchards Commons Offsite & Onsite Civil

Contract Value

$1,706,000

Location

Orchards Commons, UBC Campus

Completion Date

March 31, 2016

Description

Offsite work includes installation of storm, sanitary, water, hydro/tel and gas mains on busy West Mall and Agronomy Road around the new Vantage College facilities. Trench excavation up to six meters deep, conflict avoidance with existing utilities, and traffic management present constant challenges for the crew. Onsite work includes installation of storm, sanitary mains as well a 175m3 sistern system consists of 2.4m x 2.4m segments of precast box culvert 5m deep, all done in extremely confined space.