careers@hallconstructors.com

Projects | Hall Constructors

showing 1 to 10 of 82 on page 1 | 1  2  3  4  5  6  7  8  9    
Contract Value

$104,000,000

Location

4711 Grant McConachie Way, Richmond, BC

Completion Date

September 30, 2020

Description

Vancouver International Airport (YVR) Core Project is one of the largest expansion Projects currently underway at YVR. This Project includes a new Central Utility Building, a new Ground Transportation Facility, relocation and installation of new utilities, installation of electrical duct-bank and district energy piping (connecting the Central Utility Building to the Terminal). HALL's scope includes excavation of both buildings, construction of two pump stations, all utility relocates, installation of all new utilities including electrical duck-banks, district energy pipes, backfill around the buildings, tunnelling across the main road, demolition of existing pump station and associated works. A part of work is within the terminal.

Contract Value

$32,200,000

Location

Oakridge Mall, 650 W 41st Ave, Vancouver

Completion Date

May 1, 2020

Description

The Oakridge Offsite Civil Utilities project is a comprehensive utility upgrade package that will prepare Vancouver's infrastructure to handle the demands of the 7x high rise towers beings built on the Oakridge Mall property.

The package includes:

  • Over 1900 meters of large diameter concrete storm and sanitary sewer installations with depths exceeding 9 meters.
  • A full municipal water system upgrade for the area.
  • New BC Hydro distribution installations.
  • Demolition of a vehicular underpass, including works to facilitate upgrades to the existing BC Hydro transmission duct bank in the area.
  • A roads, signals and street light upgrade package.
  • And, other miscellaneous demolition works.
Contract Value

$25,000,000

Location

95 Brooksbank Avenue

Completion Date

October 31, 2019

Description

G3 Terminal is a new export grain terminal currently under construction in North Vancouver. HALL is responsible for delivering all excavation and civil works (approx. $25M contract) which started in March 2017 with expected completion by October 2019. HALL is responsible for delivering all civil aspects including:

  • Mass Excavation & Placement (200,000m3)
  • Utility Installation (12km of Water/Storm/Sanitary)
  • Storm/Sanitary Pump Stations
  • MSE Wall Construction (2850m2)

Project Highlights:

  • Over 80,000 Man Hours worked and we have not yet experienced a LTI or serious safety incident.
  • Completed a series of critical lifts including a concrete headwall for the storm outlet weighing in at 17,500kg
  • Over 200,000MT of gravels imported to site via barge

Overall HALL's contribution has helped G3 deliver this grain terminal and will help ensure global competitiveness in moving agricultural commodities from Canada into the World Markets. Primary materials handles at the new facility will include wheat, soybeans, canola, peas and corn.

Contract Value

$3,300,000

Location

1365 Davie Street, Vancouver, B.C.

Completion Date

March 31, 2019

Description

This 45,000 m3 excavation and shoring project was completed for Marcon Construction in late 2018 and early 2019 to assist in the construction of this modern twin tower development in Vancouver’s West End. The schedule was a major factor on this project and Hall Constructors was able to deliver the excavation on time and on budget.

Contract Value

$2,600,000

Location

401 SW Marine Drive, Vancouver

Completion Date

January 2, 2018

Description

This 65,000 m3 excavation and shoring project was completed for Centreville Construction in late 2016 and early 2017 to assist in the construction of 3 high rise apartments near the Canada Line. It consisted of 42 steel piles, 20,000 lineal feet of soil anchors, and 38,000 square feet of shotcrete shoring. The biggest challenge on this job was dealing with the large amount of rain and snow encountered throughout the fall and winter.

Contract Value

$1,690,000

Location

2289 Bellevue Avenue, West Vancouver

Completion Date

January 2, 2018

Description

Hall Constructors was contracted by Cressey Developments to complete this 31,000 m3 excavation and shoring project associated with a new residential development on the south side of Marine Drive in West Vancouver. The bottom portion of the excavation proved difficult due to very dense sandstone and siltstone which required extensive hoe-ramming in order to break up and remove the soils from site.

Contract Value

$1,200,000

Location

7864 208 Street, Langley

Completion Date

January 2, 2018

Description

This 65,000 m3 excavation and shoring project was completed for ENM Construction in late 2016 and early 2017 to assist in the construction of a midrise apartment in Northwest Langley. The site was large enough that no shotcrete shoring was required and all sides of the excavation were sloped. The biggest challenge on this job was dealing with the large amount of rain and snow encountered throughout the fall and winter.

Contract Value

$805,000

Location

5415 Lougheed Highway, Burnaby

Completion Date

January 2, 2018

Description

This 19,000 m3 excavation and shoring project was completed for Marcon Construction in late 2016 and early 2017 to assist in the construction of a townhouse development along Lougheed Highway. It consisted of 6,000 lineal feet of soil anchors, and 9,300 square feet of shotcrete shoring. The biggest challenge on this job was dealing with the large amount of groundwater which infiltrated the site from the north side.

Contract Value

$7,705,577.25

Location

Vancouver Landfill

Completion Date

November 1, 2017

Description

Work involves the installation of a layered cap onto a prepared, filled landfill or landfill area. The layers which make up the layered cap consist respectively of gravel, sand, geomembrane, geotextile and topsoil, with vegetation planted in the topsoil layer. In addition, gas works, including vertical extraction wells, piping/connections and appurtenances integrated with the layered closure system, are also installed.

The construction/installation of gas works within the Phase 3 SE and Phase 3NE areas are included in the Work. The City’s Consultant has prepared the Specifications and Drawings for the Work which includes, but is not limited to, the following work outlined further within Schedule 2 – Specifications and Drawings:

  • Earthworks
  • Landfill Closure
  • Leachate Management Upgrades
  • Surface Water Management Upgrades
  • Landfill Gas Management Upgrades
  • Infrastructure Upgrades and Miscellaneous Works
Contract Value

$5,002,000

Location

McKinley Beach Drive, Kelowna, BC

Completion Date

October 31, 2017

showing 1 to 10 of 82 on page 1 | 1  2  3  4  5  6  7  8  9