careers@hallconstructors.com

Projects | Hall Constructors

showing 21 to 30 of 82 on page 3 |     1  2  3  4  5  6  7  8  9    
Contract Value

$8,127,000

Location

Surrey, B.C.

Completion Date

May 31, 2016

Description

Widening existing 2-lane arterial connector to Hwy 1 to four lanes. Clearing, excavation, replacement of storm, sanitary & water services to existing homes, 1500m2 retaining wall, new catchbasins, granular base & subbase, new curbs & sidewalks, asphalt paving, decorative handrail, relocation of BC Hydro & Telus infrastructure, upgrading signalizing three intersections, streetlighting & property restoration. Main challenge is to maintain continuous two-lane traffic on paved surface and continuous access to private properties whilst building the new roadway and utilities.

Contract Value

$800,000

Location

Aberdeen Avenue, between Bond Street & Lansdowne Drive, Coquitlam

Completion Date

April 30, 2016

Description

Storm Culvert work began with the demolition of an existing concrete headwall and box culvert. The inlet structure was replaced by a fibreglass headwall and 1350mm concrete pipe connected to a 3,050mm x 3,050mm box manhole 6m deep. The 1350mm pipe was then extended 100m from the manhole and tied into an existing CMP. Installation of the box manhole proved very difficult due to the extreme wet weather, the underlying wet and soft clay supporting the box manhole and the proximity to the guideway. The Roadwork portion included grading, paving, concrete curb and gutter and street lighting on Aberdeen Avenue. Work on Barnet Highway involved realignment of traffic island to effect the change in traffic pattern entering Aberdeen Avenue.

Contract Value

$2,237,000

Location

West Mall & Agronomy Road, UBC

Completion Date

March 31, 2016

Description

Haul & dispose off site 25,000m3 of bulk & detailed excavation, backfill behind external perimeter walls and installation of 1,800 lm of IBO anchors and 1,000 m2 of shotcrete shoring.

Contract Value

$1,706,000

Location

Orchards Commons, UBC Campus

Completion Date

March 31, 2016

Description

Offsite work includes installation of storm, sanitary, water, hydro/tel and gas mains on busy West Mall and Agronomy Road around the new Vantage College facilities. Trench excavation up to six meters deep, conflict avoidance with existing utilities, and traffic management present constant challenges for the crew. Onsite work includes installation of storm, sanitary mains as well a 175m3 sistern system consists of 2.4m x 2.4m segments of precast box culvert 5m deep, all done in extremely confined space.

Contract Value

$4,000,000

Location

5501 Boundary Rd, Vancouver

Completion Date

March 18, 2016

Description

The contract for this project involved utility relocation, as well as excavation and shoring for Phase 2 of Wall Financial's Central Park project. First, Hall Constructors relocated 110 meters of 1350 diameter storm pipe and 110 meters of 750 diameter sanitary pipe which are both owned by Metro Vancouver. Once those utilities were moved off of the property, Hall completed the 43,000 m3 excavation by using a combination of secant piles and conventional shotcrete to shore the dig. This project also included installation of BC Hydro, Telus and storm/sanitary services for both phases of the development.

Contract Value

$3,234,000

Location

Burnaby, BC

Completion Date

January 22, 2016

Description

Scope of the project was to place two individual classes of aggregate to a total depth of 2.17 meters for the total length of the 2000 lm of bored tunnel.

Challenges:

  • To meet the schedule crews had to work 22 hours per day
  • Access was restricted to the north portal on the north end of the tunnel.
  • The base of the north portal was approximately 7 meters below ground surface.
  • A conveying system and chute had to be installed to transfer aggregates from the stockpiles at ground level to the trucks below.
  • All equipment had to be lowered into the portal with a 210 tonne Crane
  • Height of the tunnel was not sufficient for conventional trucks to dump. To facilitate moving the aggregate Cat 730 articulate trucks with ejector boxes were used.
  • Because there insufficient room to turn, the four 730 Cat trucks to turn they had to back into the tunnel after they were loaded and drive out.
  • A small dozer and compactor were used in the tunnel to place and compact the aggregate in the tunnel.
Contract Value

$14,500,000

Location

39 Smithe Street, Vancouver, BC

Completion Date

January 15, 2016

Description

Project consisted of select demolition of BC Place, Jet Grout Piles, Driven Pile Piles, Bulk / Detailed / Mechanical Excavation complete with Shotcrete and Anchor Shoring system. Total volume of material removed was 160,000 m3 of which approximately 45,000 m3 was contaminated. Schedule was a major factor on this project and Hall Constructors was able to deliver the excavation 2 months ahead of schedule.

Contract Value

$4,350,000

Location

Vancouver Landfill, Delta BC

Completion Date

January 8, 2016

Description

-Leachate Pump Station upgrades including application of poly-urea coating in leachate tanks, several road crossings, HDPE air, leachate and gas pipe-lines, supply & installation of gas well de-watering system

Contract Value

$3,780,000

Location

1300 Block of Marine Drive, West Vancouver, BC

Completion Date

December 21, 2015

Description

Project consisted of site preparation works to allow for the installation of 354 - 1 metre diameter Secant Piles to an average depth of 17 metres below existing grade.

Contract Value

$1,115,000

Location

3205 Mountain Highway

Completion Date

December 15, 2015

Description

This 15,000 m3 excavation and shoring project was completed for Marcon Construction in 2015. Though the site proved difficult, Hall was able to work with the Owner to deliver the excavation on time. Extra measures were taken to ensure that the neighboring creek was protected and that silt from the excavation was diverted away from the waterway. Hall also used it's ocean dumping facility to provide the most economic soil disposal option on this project.

showing 21 to 30 of 82 on page 3 |     1  2  3  4  5  6  7  8  9