careers@hallconstructors.com

Projects | Hall Constructors

showing 21 to 30 of 78 on page 3 |     1  2  3  4  5  6  7  8    
Contract Value

$3,325,000

Location

Ioco Road & Barnet Highway, Port Moody, BC

Completion Date

March 31, 2014

Description

Project consisted of the Bulk/Detailed Excavation of approximately 17,000 m3 for the East and West Head House structures. The excavation was supported by a shoring design consisting of pipe piles, fiberglass anchors, IBO Anchors and Secant Piles. Once these excavations were completed, we completed a 8,000 m3 excavation in 48 hours to facilitate the pushing of the Box Tunnel followed by the rebuilding of the roadway in 24 hours.

Contract Value

$3,234,000

Location

Burnaby, BC

Completion Date

January 22, 2016

Description

Scope of the project was to place two individual classes of aggregate to a total depth of 2.17 meters for the total length of the 2000 lm of bored tunnel.

Challenges:

  • To meet the schedule crews had to work 22 hours per day
  • Access was restricted to the north portal on the north end of the tunnel.
  • The base of the north portal was approximately 7 meters below ground surface.
  • A conveying system and chute had to be installed to transfer aggregates from the stockpiles at ground level to the trucks below.
  • All equipment had to be lowered into the portal with a 210 tonne Crane
  • Height of the tunnel was not sufficient for conventional trucks to dump. To facilitate moving the aggregate Cat 730 articulate trucks with ejector boxes were used.
  • Because there insufficient room to turn, the four 730 Cat trucks to turn they had to back into the tunnel after they were loaded and drive out.
  • A small dozer and compactor were used in the tunnel to place and compact the aggregate in the tunnel.
Contract Value

$2,830,000

Location

Coquitlam, BC

Completion Date

February 29, 2012

Description

Construction started in July 2011 with the aim being to prepare a proposed site at Pipeline Road and David Avenue in Port Coquitlam for construction of a multi-story apartment complex complete with 3 levels of parkade. Preparation of the site involved pile driving, shotcrete and anchoring, bulk excavation, detail excavation and rock removal. A large portion of the work was bulk excavation with 60,000 cubic metres removed from site. Project completion was February 2012.

Contract Value

$2,635,000

Location

Nordel Way, Surrey, BC

Completion Date

June 30, 2011

Description

The project consisted of widening Nordel Way to implement left-turn lanes at Brooke Road and Shepherd Way intersections along with the installation of drainage improvements and a centre median along Nordel Way. To accomplish this work a retaining wall was required in an area that was considered to be environmentally sensitive as well as all new street lights and intersection signals were installed. At the completion a sound barrier wall was constructed on both side of Nordel Way.

Contract Value

$2,600,000

Location

401 SW Marine Drive, Vancouver

Completion Date

January 2, 2018

Description

This 65,000 m3 excavation and shoring project was completed for Centreville Construction in late 2016 and early 2017 to assist in the construction of 3 high rise apartments near the Canada Line. It consisted of 42 steel piles, 20,000 lineal feet of soil anchors, and 38,000 square feet of shotcrete shoring. The biggest challenge on this job was dealing with the large amount of rain and snow encountered throughout the fall and winter.

Contract Value

$2,530,000

Location

1308 Lonsdale Ave, North Vancouver

Completion Date

April 30, 2017

Description

Hall Constructors is completing the offsite civil work on this project for Onni. The work includes new curb, sidewalk and asphalt for the road surrounding the site, as well as extensive BC Hydro, street light and intersection signal upgrades. Hall has worked extensively with the Owner, City and local businesses to ensure that construction is safe and that disruptions are kept to a minimum. This is especially important due to the close proximity of the Lions Gate Hospital, city hall, fire hall, RCMP detachment and surrounding residential buildings.

Contract Value

$2,500,000

Completion Date

November 30, 2014

Description

Storm and Sanitary upgrades, road re-construction and improvements to Knight Street, Jacombs Road and Sweden Way, BC Hydro and Telus civil installation.

Contract Value

$2,400,000

Location

2513 Clarke St, Port Moody

Completion Date

December 31, 2016

Description

This project includes secant pile drilling and bulk excavation of 24,000 m3 of material for Townline Construction. The poor soil conditions at the footing level require a raft slab foundation.

Contract Value

$2,330,000

Location

1779 Douglas Rd, Burnaby

Completion Date

July 31, 2013

Description

This 40,000 m3 excavation and shoring project made wade way for a high-rise residential tower in Burnaby’s Brentwood neighborhood, which was managed by Marcon Construction. Under approval from Environment Canada, Hall Constructors implemented ocean disposal of the clean, excavated material, as this is the most effective and economical option for the Owner.

Contract Value

$2,320,000

Location

88 West 1st Ave, Vancouver

Completion Date

July 31, 2013

Description

Hall Constructors completed this 43,000 m3 excavation and shoring project for Mondiale Development in 2013. The site was located on the historical ocean shoreline and had previously been infilled with contaminated material. Hall worked with the Owner and Environmental Consultant to send all contaminants to appropriate remediation facilities, then obtained approval from Environment Canada to dispose of the clean, native material via ocean dumping.

showing 21 to 30 of 78 on page 3 |     1  2  3  4  5  6  7  8