careers@hallconstructors.com

Projects | Hall Constructors

showing 31 to 40 of 82 on page 4 |     1  2  3  4  5  6  7  8  9    
Contract Value

$603,000

Location

7928 & 7988 Yukon Street, Vancouver, BC

Completion Date

December 15, 2015

Description

The project consisted of an approximate 13,100 m3 Bulk & Detail excavation including shotcrete & Anchor shoring. Limited access and a long and narrow site made this project a challenge to complete on schedule.

Contract Value

$4,800,000

Location

Richmond, BC

Completion Date

November 30, 2015

Description

Installation of a 1200 mm dia Concrete Storm Sewer, road widening from two lanes to four, addition of a multi-use bike path, traffic signalization and street-lighting.

Contract Value

$3,650,000

Location

3075 Takaya Drive, North Vancouver

Completion Date

November 30, 2015

Description

Excavated and hauled offsite 46,000 m3 of non-contaminated and 10,000 m3 of contaminated (CL+ & RL+) soil. Placed 11,000 m3 of imported fill. In addition, 3,700m2 of SedimentLok 200+ m2 of SierraScape retaining wall were built for erosion control and slope stablization. Job completed on budget and ahead of schedule.

Contract Value

$1,300,000

Location

Taylor Way and Keith Road in West Vancouver

Completion Date

November 1, 2015

Description

Excavation and shoring for a senior care home living complex. This project included the construction or permanent shotcrete walls that were finished to match the natural rock outcrops in the area.

Contract Value

$382,400

Location

19498 - 92 Avenue, Surrey, B.C.

Completion Date

October 15, 2015

Description

Clearing, excavation, granular fill, gravel installation, and asphalt paving. BD Hall proposed a modification of pavement structure which permitted installation of asphalt paving within three weeks of startup during busy paving season - this allowed Finning additional time to re-position equipment to other facilities prior to arrival of new equipment.

Contract Value

$1,535,000

Location

57 Sixth Street, New Westminster

Completion Date

October 10, 2015

Description

Hall Constructors was contracted by Metro-Can Construction to complete this 25,000 m3 excavation & shoring project. The bottom half of the excavation proved difficult as significant groundwater was discovered as digging progressed. Conventional pumping could not keep up to the water in the sandy ground, and Hall worked with the Owner to install a dewatering system to lower the local water table. In the end, Hall wrapped up another successful project by craning their excavator out of the excavation.

Contract Value

$8,408,000

Location

Burnaby Campus of Simon Fraser University

Completion Date

September 30, 2015

Description

Project included 3.5km of road re-construction, 7,000m of curb & gutter, 700m of concrete sidewalk, a roundabout, 3km of multi-use path, intersection improvements, street lighting, sewer and watermain construction, detention pond and landscape works. Scope: - Remove existing concrete and asphalt road - Reuse road concrete as base of multi-use pathway - Reconstruct road, curbs and gutters - Construct new detention pond - Lighting and signalized intersection - Landscaping

Contract Value

$2,030,000

Location

UBC Athletics Precinct - Wesbrook Mall & 16th Avenue, UBC

Completion Date

September 30, 2015

Description

Faced with the challenge of a very tight schedule and proximity to existing facilities, the crew installed storm, sanitary, water, hydro/tel, gas mains and a 250 m3 cast-in-place concrete detention tank. The project finished on time and on budget.

Contract Value

$1,840,000

Location

University Boulevard & East Mall, UBC Campus

Completion Date

September 30, 2015

Description

Scope of work includes ** Watermain upgrade, ** Demolition of existing sidewalk, road structure and concrete slab, replaced with new landscaping features and concrete pavers. ** Construction of a new 450m3 cast in place concrete detention tank.

Contract Value

$1,018,000

Location

1105 & 1121 Seymour Street

Completion Date

August 15, 2015

Description

This project consisted of an approximate 14,600 m3 Bulk & Detailed Excavation including Shotcrete & Anchor shoring system. The challenge for this project was working very near sensitive utilities including several 600 KVolt lines and associated vaults. Extra caution was necessary but also ensuring the project was completed as scheduled.

showing 31 to 40 of 82 on page 4 |     1  2  3  4  5  6  7  8  9