careers@hallconstructors.com

Projects | Hall Constructors

showing 51 to 60 of 79 on page 6 |     2  3  4  5  6  7  8    
Contract Value

$10,900,000

Location

Vancouver Landfill, Delta BC

Completion Date

August 1, 2014

Description

This project consisted of the supply and installation of a geo-membrane closure system (5.5 Ha area), gas extraction well drilling, excavation, grading, construction of a leachate and gas collection system, gas system upgrades, a 4 Ha double-lined surface water detention pond and erosion and sediment control measure. All work was substantially complete within a short time of 3.5 months.

Contract Value

$1,020,000

Location

633 Main St, Vancouver

Completion Date

June 30, 2014

Description

This excavation and shoring project had the unique challenge of being located next to a BC Hydro substation, which resulted in a extensive network of underground high voltage conduits. Hall Constructions worked closely with Axiom Builders and the geotechnical engineer to locate all underground utilities and come up with a shoring design that allowed the excavation to proceed without damaging any conduits.

Contract Value

$2,024,000

Location

Downtown, Vancouver, BC

Completion Date

May 15, 2014

Description

Scope includes removal of existing pumps and electrical works, installation of temporary lighting and ventilation system and filling this 800m long tunnel with cellular concrete.

Contract Value

$1,080,000

Location

1588 E Hasting St, Vancouver

Completion Date

April 30, 2014

Description

Hall Constructors completed this excavation and shoring project for Metro-Can Construction in 2014. The final 4 storey building was a significant upgrade to the community, adding commercial shops to the main floor, with residential units above. Hall was able to excavate through the bedrock at the bottom of the excavation and used ocean disposal for the clean soil to maintain the project schedule.

Contract Value

$420,000

Location

1388 Continental St, Vancouver

Completion Date

April 21, 2014

Description

Hall Constructor completed this small excavation and shoring project for Cressey Developments. The major challenges on this site were working on a small building footprint with limited access and sloped surroundings. Hall also worked closely with the geotechnical Engineer to ensure that underpinning of the neighboring building and Granville St Bridge footings was done safely and correctly.

Contract Value

$3,325,000

Location

Ioco Road & Barnet Highway, Port Moody, BC

Completion Date

March 31, 2014

Description

Project consisted of the Bulk/Detailed Excavation of approximately 17,000 m3 for the East and West Head House structures. The excavation was supported by a shoring design consisting of pipe piles, fiberglass anchors, IBO Anchors and Secant Piles. Once these excavations were completed, we completed a 8,000 m3 excavation in 48 hours to facilitate the pushing of the Box Tunnel followed by the rebuilding of the roadway in 24 hours.

Contract Value

$603,700

Location

70th Ave & 194A Street, Surrey, BC

Completion Date

January 31, 2014

Description

This project consisted of a roadworks upgrade including utilities and streetlights.

Contract Value

$1,590,000

Location

500 Royal Ave, New Westminster

Completion Date

October 31, 2013

Description

Hall Constructors completed the excavation and shoring for this 118 unit condominium project, which was managed by Marcon Construction. Included in the 17,000 m3 excavation was the safe remediation of contaminated soils which were discovered during the work. As the project is located across the street from City Hall in New Westminster, much care and attention went into implementing safety measures to protect the pedestrians, vehicles and workers in this high traffic area. Hall Constructors returned to complete the road works and street lighting after the building construction was in the finishing stages.

Contract Value

$1,490,000

Location

16th Avenue & Stride Ave, Burnaby

Completion Date

October 15, 2013

Description

Hall Constructors completed the site preparation and bulk excavation for Marcon Construction on the Portraits project in Burnaby. The work for this residential condo development involves diverting the existing underground utilities, bulk excavation of 17,000 m3, shoring, detail excavation and extending the existing creek through the property. The creek work was executed during the DFO’s fisheries window to minimize impact on the existing fish habitat.

Contract Value

$2,330,000

Location

1779 Douglas Rd, Burnaby

Completion Date

July 31, 2013

Description

This 40,000 m3 excavation and shoring project made wade way for a high-rise residential tower in Burnaby’s Brentwood neighborhood, which was managed by Marcon Construction. Under approval from Environment Canada, Hall Constructors implemented ocean disposal of the clean, excavated material, as this is the most effective and economical option for the Owner.

showing 51 to 60 of 79 on page 6 |     2  3  4  5  6  7  8