careers@hallconstructors.com

Projects | Hall Constructors

showing 61 to 70 of 81 on page 7 |     3  4  5  6  7  8  9    
Contract Value

$1,490,000

Location

16th Avenue & Stride Ave, Burnaby

Completion Date

October 15, 2013

Description

Hall Constructors completed the site preparation and bulk excavation for Marcon Construction on the Portraits project in Burnaby. The work for this residential condo development involves diverting the existing underground utilities, bulk excavation of 17,000 m3, shoring, detail excavation and extending the existing creek through the property. The creek work was executed during the DFO’s fisheries window to minimize impact on the existing fish habitat.

Contract Value

$2,330,000

Location

1779 Douglas Rd, Burnaby

Completion Date

July 31, 2013

Description

This 40,000 m3 excavation and shoring project made wade way for a high-rise residential tower in Burnaby’s Brentwood neighborhood, which was managed by Marcon Construction. Under approval from Environment Canada, Hall Constructors implemented ocean disposal of the clean, excavated material, as this is the most effective and economical option for the Owner.

Contract Value

$2,320,000

Location

88 West 1st Ave, Vancouver

Completion Date

July 31, 2013

Description

Hall Constructors completed this 43,000 m3 excavation and shoring project for Mondiale Development in 2013. The site was located on the historical ocean shoreline and had previously been infilled with contaminated material. Hall worked with the Owner and Environmental Consultant to send all contaminants to appropriate remediation facilities, then obtained approval from Environment Canada to dispose of the clean, native material via ocean dumping.

Contract Value

$825,000

Location

135 W 2nd St. North Vancouver

Completion Date

June 30, 2013

Description

Hall Constructors completed this 13,000 m3 excavation for Metro-Can Construction in North Vancouver. Contaminated soil was identified at the outset, and Hall worked through the remediation process with the Owner to minimze costs and delays. Though the ground conditions were difficult and the access was very limited, Hall completed the bulk excavation, shoring and detail excavation for a successful handover to the form work contractor.

Contract Value

$4,375,000

Location

Marine Drive and Taylor Way, District of West Vancouver, BC

Completion Date

May 15, 2013

Description

Scope includes removal of two overpass structures on Marine Drive, installation of underground utilities, construction of signalized intersection at overpass location, signalization of another intersection, re-alignment of Parking Lots and Landscaping.

Contract Value

$450,000

Location

848 Royal Ave, New Westminster

Completion Date

March 27, 2013

Description

Hall Constructors was contracted by Chysik Project Management to complete the excavation and shoring for the sedoncd phase of a townhouse development on Royal Avenue in New Westminster. Hall utilized the sloping grade surrounding this site to complete the 7,500 m3 excavation quickly and efficiently. Attention to detail was necessary for the shoring on the zero wall which was constructed on three sides of the site.

Contract Value

$560,000

Location

4000 Main St, Vancouver

Completion Date

February 18, 2013

Description

This property at Main St and King Edward Ave in Vancouver was previously occupied by a gas station resulting in widespread gasoline contamination in the site soil. Although the majority of the soil within the property was removed as part of the initial remediation process by others, Hall identified and removed remaining soil that had contamination levels exceeding acceptable standards. The remaining 3,500 m3 of material was used to build ramps and pads to complete the pile driving and shotcrete shoring. Upon completion of the shoring, all excess material was hauled off site and detail excavation was completed for the foundation of this mixed-use residential development.

Contract Value

$1,480,000

Location

Vancouver, BC

Completion Date

December 31, 2012

Description

The Great Northern Way Campus Lot “O” project involves clearing and grubbing and off-site disposal of vegetation and debris from the work area, installation and maintenance of erosion and sediment control facilities, stripping and earthworks for approximately 36,000 metric tonnes of road embankment construction, temporary lock-block retaining wall and retaining wall drainage.

Contract Value

$1,387,000

Location

Coquitlam, BC

Completion Date

October 31, 2012

Description

Site servicing, utility installation and road works for a 34 lot residential subdivision located in Coquitlam.

Contract Value

$1,277,000

Location

148th Street and 61 Avenue, Surrey, BC.

Completion Date

September 30, 2012

Description

On & off-site servicing for a 91 unit townhouse site. The project consists of site servicing for a 91 unit townhouse site which includes 500m of new road construction, storm, sanitary and water services, electrical, hydro, Telus and cable connections. The project also consists of significant onsite earth works and approximately 100 lm of retaining construction.

showing 61 to 70 of 81 on page 7 |     3  4  5  6  7  8  9