careers@hallconstructors.com

Projects | Hall Constructors

showing 71 to 80 of 82 on page 8 |     4  5  6  7  8  9  
Contract Value

$1,277,000

Location

148th Street and 61 Avenue, Surrey, BC.

Completion Date

September 30, 2012

Description

On & off-site servicing for a 91 unit townhouse site. The project consists of site servicing for a 91 unit townhouse site which includes 500m of new road construction, storm, sanitary and water services, electrical, hydro, Telus and cable connections. The project also consists of significant onsite earth works and approximately 100 lm of retaining construction.

Contract Value

$1,130,000

Location

15241 Thrift Ave, White Rock

Completion Date

September 30, 2012

Description

The construction of this new mixed-use residential development in White Rock, BC was managed by Macron construction, with the excavation and shoring completed by Hall Constructors. Contaminated soil was encountered at the outset of the 14,000 m3 excavation and sent to a remediation facility for proper disposal. The features of this project were the raking shores and pile driving, which were implemented for one wall where conventional shoring was not possible.

Contract Value

$1,251,000

Location

76A Ave & 156 St, Surrey, BC.

Completion Date

August 31, 2012

Description

24 Lot Subdivision and Site Servicing. Scope of work consisting of tree clearing and lot preparation, utility install, roads and hard surface treatments.

Contract Value

$300,000

Location

1190 West 6th Avenue, Vancouver

Completion Date

August 31, 2012

Description

Hall Constructors completed the excavation and shoring for this townhome development at 6th Ave & Alder St in Vancouver, working with Chysik Project Management. Tight working constraints, hard sandstone boulders and extremely steep grade of the site added to the complexity of the project.

Contract Value

$1,236,000

Location

West end of the UBC campus

Completion Date

May 31, 2012

Description

This new UBC mixed development is managed by Ledcor Construction. The building will serve as residence and lecture hall for students. Excavation began in late January 2012, and was completed in May 2012. The total excavation volume of this phase was approximately 17,000m3. The challenges of this project were the pedestrian traffic management and aggressive schedule objectives.

Contract Value

$824,000

Location

East Vancouver

Completion Date

May 31, 2012

Description

Construction started in January 2012. The Sesame is a new East Vancouver residential development by Marcon Construction Ltd. Hall Constructors was responsible for the excavation, shoring and mechanical trenching of the four storey wood frame structure with two levels underground parkade. The excavation of 200m3 of bed rocks and the traffic management of adjacent shopping center traffic were some of the challenges we faced during this project. The total excavation volume was approximately 16,000m3 and was completed in May 2012.

Contract Value

$418,000

Location

UBC Campus, Vancouver, BC

Completion Date

May 31, 2012

Description
This is the second part of the UBC Ponderosa development. The east and the west building are separated by the Lower Mall and are located at the west end of the UBC campus. Excavation began late February, and was completed in May 2012. The total excavation volume of this building was approximately 3,000m3.
Contract Value

$2,830,000

Location

Coquitlam, BC

Completion Date

February 29, 2012

Description

Construction started in July 2011 with the aim being to prepare a proposed site at Pipeline Road and David Avenue in Port Coquitlam for construction of a multi-story apartment complex complete with 3 levels of parkade. Preparation of the site involved pile driving, shotcrete and anchoring, bulk excavation, detail excavation and rock removal. A large portion of the work was bulk excavation with 60,000 cubic metres removed from site. Project completion was February 2012.

Contract Value

$24,000,000

Location

Near Hudson’s Hope, BC

Completion Date

November 30, 2011

Description

On March 25, 2011, Hall Constructors was awarded the contract to perform slope stabilization works above the spillway at BC Hydro’s WAC Bennett Dam near Hudson’s Hope, BC. This project will consist of blasting and excavating over 230,000 cubic yards of rock as well as installing anchors and shotcrete on the final slopes above the spillway. Upon completion of the blasting, protective rock mesh will be installed to further minimize the possibility of rock fall. This project was completed in November, 2011.

Contract Value

$10,000,000

Location

96th Avenue 160th to 164th in Surrey

Completion Date

August 31, 2011

Description

The 96th Avenue project involves ultimate Arterial Road widening including storm sewers, water mains, curb & gutter, paving, sidewalks, street lighting, traffic signals, retaining walls, preloading and bridge construction in the City of Surrey along 96th Avenue between 160th Street and 168th Street. One of Surrey’s major federal stimulation funded projects, a major portion of the project was completed in March, 2011. A second phase of the bridge crossing Serpentine River was completed in the summer of 2011. The major challenge of the project is the road construction between 160th to 164th. Construction in the area involves excavation and road construction work on existing properties on both sides of the Arterial. Major property restoration and reconfiguration to the properties in the area are part of the work in this challenging project.

showing 71 to 80 of 82 on page 8 |     4  5  6  7  8  9